Reliable Anchoring System
HUAHAI rubber dam can be fixed to the concrete foundation using either a single or double line of anchors, forming a sealed rubber dam body. Inflated with water or air, the rubber dam can be operated to increase water level or discharge flood. The anchoring system should ensure 100% air and water tight and increase the stability of the rubber body and reduce the possibility of vibration. There are many kinds of anchoring structures for rubber dam, the most commonly used are bolt anchorage and wedge anchorage. The anchoring system of HUAHAI rubber dam will design to best suit clients’ needs.
橡膠壩安裝三維展示圖

3D display of rubber dam installation

錨固槽大樣圖(楔塊改螺栓錨固槽圖)

Wedge anchorage changing into bolt anchorage

橡膠壩錨固圖

Anchoring system of rubber dam

Rubber dam installation
The size of the rubber dam bags and base rubber sheet produced by HUAHAI will be strictly checked before the rubber dam leaving the factory. The anchoring line and the anchoring center line will be drawn on the rubber body, and the upstream and downstream marks will be made in the conspicuous position.
01 Installing bolts and embedded plates
Installing bolts and embedded plates
02 Installing anchors
Installing anchors
03 Cast in concrete
Cast in concrete
04 Unrolling the base rubber sheet
Unrolling the base rubber sheet
05 Installing water-stopped or air-stopped rubber sheet
Installing water-stopped or air-stopped rubber sheet
06 Unrolling the rubber body
Unrolling the rubber body
07 Drilling anchor holes
Drilling anchor holes
08 Installing the strengthened rubber sheet
Installing the strengthened rubber sheet
09 Setting clamping plates and tightening anchor bolts
Setting clamping plates and tightening anchor bolts
10 Conducting inflation test
Conducting inflation test
11 Rubber dam operation
Rubber dam operation
Collapsible Weir Installation
01 Drilling holes in the rubber air bladder
Drilling holes in the rubber air bladder
02 Installing nozzles and pipes
Installing nozzles and pipes
03 Completion of rubber bladder
Completion of rubber bladder
04 Installing soft connection with steel gate
Installing soft connection with steel gate
05 Hosting the steel gate panel in position
Hosting the steel gate panel in position
06 Setting clamping plates
Setting clamping plates
07 Installing side air-stopped rubber sheet
Installing side air-stopped rubber sheet
08 Installing limit belt
Installing limit belt
09 Inflation test and completion
Inflation test and completion
10 Operation
Operation